StudyVib

Architecture

Professional Practice Examination (PPE)

Professional practice examination for architects; on passing, the architect is entered onto the Standing Register of Registered Architects.

Practice questions
203
Flashcards
150
Topics
15
Mock exam
100 questions · 120 min · pass 50%

What the Professional Practice Examination (PPE) covers

Our questions are organised by subject and topic, following the exam syllabus.

Architectural Professional Practice

  • Registration, Ethics & Client Duty 23 Qs · 16 cards
  • Project Delivery & Contract Administration 24 Qs · 17 cards
  • Planning, Building Control & Sustainability 21 Qs · 14 cards
  • Practice Management & Fees 8 Qs · 6 cards
  • Construction Law & Disputes 8 Qs · 6 cards

Construction & Project Management

  • Project Management 13 Qs · 8 cards
  • Contracts & Procurement 12 Qs · 8 cards
  • Construction & Site Management 10 Qs · 7 cards

Architectural Design & Technology

  • Climate-Responsive Design in Ghana 18 Qs · 15 cards
  • Fire Safety & Accessibility 12 Qs · 8 cards
  • Building Technology & Materials 16 Qs · 15 cards
  • Site Analysis & Briefing 10 Qs · 8 cards
  • Heritage, Urban Design & Housing 10 Qs · 7 cards
  • Building Services & Sustainability 8 Qs · 6 cards
  • Structures & Services Coordination 10 Qs · 9 cards

Sample Architecture practice questions

Try these 12 questions from different topics. Open "Show answer" to check yourself and read the explanation.

  1. Question 1 · Registration, Ethics & Client Duty

    A client asks a probationer architect to describe themselves publicly as a registered architect before passing the PPE. What is the most appropriate response?

    1. A.Decline and use only the professional title permitted by the current register
    2. B.Use the title because the client requested it
    3. C.Use the title only on social media
    4. D.Use the title if no fee is charged
    Show answer

    Answer: A. Decline and use only the professional title permitted by the current register

    Protected professional titles and registration status should be represented accurately to clients and the public.

  2. Question 2 · Project Delivery & Contract Administration

    A client requests a material change during construction that may affect cost and completion time. What should the architect do first?

    1. A.Tell the contractor to proceed verbally without records
    2. B.Document and evaluate the proposed variation through the authorized contract process
    3. C.Hide the likely cost effect from the client
    4. D.Change the drawings after completion
    Show answer

    Answer: B. Document and evaluate the proposed variation through the authorized contract process

    Controlled variation procedures preserve authority, scope, cost, time and accountability.

  3. Question 3 · Planning, Building Control & Sustainability

    Before construction begins on a project requiring statutory approval, what should the architect confirm?

    1. A.That furniture has already been purchased
    2. B.That the contractor can bypass the assembly
    3. C.That the required planning and building approvals have been obtained
    4. D.That only a verbal neighbourhood approval exists
    Show answer

    Answer: C. That the required planning and building approvals have been obtained

    Professional project delivery includes compliance with applicable planning, building and environmental requirements.

  4. Question 4 · Practice Management & Fees

    An architect's fee of 6% on a construction cost of GH₵2,000,000 is:

    1. A.GH₵12,000
    2. B.GH₵1,200,000
    3. C.GH₵120,000
    4. D.GH₵60,000
    Show answer

    Answer: C. GH₵120,000

    0.06 × 2,000,000.

  5. Question 5 · Construction Law & Disputes

    An architect who negligently designs a building that causes injury may be liable in:

    1. A.Tort (negligence) and possibly contract
    2. B.Criminal law only, never in civil law
    3. C.Customary law only
    4. D.No law at all
    Show answer

    Answer: A. Tort (negligence) and possibly contract

    Liability may be owed to the client and to third parties.

  6. Question 6 · Project Management

    The critical path in a project network is the:

    1. A.Longest path, setting the minimum duration
    2. B.Shortest path through the network of activities
    3. C.Path with the most activities
    4. D.Path with the most resources
    Show answer

    Answer: A. Longest path, setting the minimum duration

    Delays on critical activities delay the whole project.

  7. Question 7 · Contracts & Procurement

    FIDIC contracts are widely used for:

    1. A.Employment contracts for engineering staff
    2. B.International construction projects
    3. C.Land sales
    4. D.Insurance policies
    Show answer

    Answer: B. International construction projects

    The Red Book is for construction designed by the employer.

  8. Question 8 · Construction & Site Management

    The standard age at which concrete cube strength is usually assessed for compliance is:

    1. A.3 days
    2. B.1 year
    3. C.28 days
    4. D.1 day
    Show answer

    Answer: C. 28 days

    7-day results give an early indication.

  9. Question 9 · Climate-Responsive Design in Ghana

    In Ghana's tropical climate, buildings are best oriented with their long axis running:

    1. A.North–south, to face the rising and setting sun
    2. B.East–west
    3. C.Diagonally in every case
    4. D.Towards the nearest road only
    Show answer

    Answer: B. East–west

    Low morning and afternoon sun on east and west walls is hard to shade.

  10. Question 10 · Fire Safety & Accessibility

    Fire safety certification of premises in Ghana is the responsibility of the:

    1. A.Architects Registration Council
    2. B.Ghana National Fire Service
    3. C.Ghana Police Service
    4. D.Environmental Protection Agency
    Show answer

    Answer: B. Ghana National Fire Service

    The Fire Service operates under Act 537 (1997).

  11. Question 11 · Building Technology & Materials

    A damp-proof course in a wall mainly prevents:

    1. A.Termite attack on roof timbers
    2. B.Heat gain through the wall
    3. C.Sound transmission
    4. D.Rising damp from the ground
    Show answer

    Answer: D. Rising damp from the ground

    It is laid near the base of walls above ground level.

  12. Question 12 · Site Analysis & Briefing

    A client brief for a building project mainly sets out:

    1. A.The contractor's tender price and programme for the works
    2. B.The architect's personal design preferences
    3. C.The client's needs, budget and timescale
    4. D.Building regulations in full
    Show answer

    Answer: C. The client's needs, budget and timescale

    A clear brief reduces costly design changes later.

Sample flashcards

Quick facts to revise. Members can study every card with Learn, Test and Match modes.

Registration body
Architects Registration Council
Architect's instruction
In writing
Planning law
Act 925 (2016), LUSPA
Fee calculation
% × construction cost
Negligent design
Tort and contract liability
Critical path
Longest path, zero float
FIDIC Red Book
Employer-designed construction
Concrete compliance age
28 days

Ready to practise the full Architecture question bank?

Free account. Practise by topic, sit timed mock exams, study flashcards and track your readiness.

Create a free account

StudyVib is an independent study platform and is not affiliated with or endorsed by the Architects Registration Council. Questions are original practice material written to reflect the syllabus; they are not past examination papers.