StudyVib

Mining Engineering

Engineering Professional Examination — Mining Engineering

Professional registration examination for mining engineers, administered under the Engineering Council of Ghana.

Practice questions
200
Flashcards
155
Topics
18
Mock exam
100 questions · 120 min · pass 50%

What the Engineering Professional Examination — Mining Engineering covers

Our questions are organised by subject and topic, following the exam syllabus.

Mining Engineering Practice

  • Mine Safety & Hazard Control 9 Qs · 6 cards
  • Ground Control & Emergency Response 12 Qs · 9 cards
  • Environmental & Professional Responsibility 10 Qs · 7 cards
  • Ghana Mining Law & Regulation 18 Qs · 15 cards
  • Surface & Underground Mining Methods 12 Qs · 9 cards
  • Drilling & Blasting 12 Qs · 9 cards
  • Mine Ventilation 8 Qs · 8 cards
  • Ghana Mining Industry 6 Qs · 7 cards
  • Mining Geology, Sampling & Surveying 10 Qs · 9 cards
  • Artisanal & Small-Scale Mining 6 Qs · 5 cards
  • Mine Equipment, Water & Tailings 8 Qs · 7 cards

Professional Engineering Practice

  • Ethics, Competence & Public Safety 13 Qs · 7 cards
  • Occupational Health & Safety 12 Qs · 9 cards
  • Risk & Project Controls 10 Qs · 7 cards
  • Engineering Economics 12 Qs · 8 cards
  • Professional Review & Quality 12 Qs · 9 cards

Mineral Processing

  • Mineral Processing & Metallurgy 20 Qs · 17 cards
  • Mine Planning & Economics 10 Qs · 7 cards

Sample Mining Engineering practice questions

Try these 12 questions from different topics. Open "Show answer" to check yourself and read the explanation.

  1. Question 1 · Mine Safety & Hazard Control

    Which control is preferable for respirable dust when technically feasible?

    1. A.Capture or suppress the dust at its source with an engineering control
    2. B.Rely only on disposable masks
    3. C.Increase the time workers spend in dust
    4. D.Remove ventilation monitoring
    Show answer

    Answer: A. Capture or suppress the dust at its source with an engineering control

    Source-based engineering controls are more reliable than controls that depend entirely on worker behaviour.

  2. Question 2 · Ground Control & Emergency Response

    Workers observe fresh cracking and falling material in an underground work area. What should happen first?

    1. A.Continue production until the shift ends
    2. B.Withdraw people from danger, isolate the area and obtain competent ground-control assessment
    3. C.Cover the crack with paint
    4. D.Send one unprotected worker to investigate alone
    Show answer

    Answer: B. Withdraw people from danger, isolate the area and obtain competent ground-control assessment

    Signs of instability require immediate protection of people and competent assessment before work resumes.

  3. Question 3 · Environmental & Professional Responsibility

    A mine-plan change could materially increase community water contamination risk. What should the engineer do?

    1. A.Hide the change from reviewers
    2. B.Assume dilution will solve every contaminant
    3. C.Assess, document and communicate the risk and require adequate controls before approval
    4. D.Approve it because environmental effects are outside engineering
    Show answer

    Answer: C. Assess, document and communicate the risk and require adequate controls before approval

    Professional responsibility includes transparent assessment and control of foreseeable public and environmental harm.

  4. Question 4 · Ghana Mining Law & Regulation

    The principal law governing mineral rights in Ghana is the:

    1. A.Lands Commission Act, 2008 (Act 767)
    2. B.Companies Act, 2019
    3. C.Minerals and Mining Act, 2006
    4. D.Petroleum Commission Act, 2011
    Show answer

    Answer: C. Minerals and Mining Act, 2006

    It has been amended several times since 2006.

  5. Question 5 · Surface & Underground Mining Methods

    A pit that must remove 600,000 t of waste to mine 150,000 t of ore has a stripping ratio of:

    1. A.0.25 : 1
    2. B.6 : 1
    3. C.4 : 1
    4. D.1.5 : 1
    Show answer

    Answer: C. 4 : 1

    Stripping ratio = waste ÷ ore.

  6. Question 6 · Drilling & Blasting

    Powder factor in blasting is expressed as:

    1. A.The number of holes per bench
    2. B.Explosive price per kilogram
    3. C.Explosive mass per tonne of rock broken
    4. D.Blast duration
    Show answer

    Answer: C. Explosive mass per tonne of rock broken

    500 kg breaking 2,000 t gives 0.25 kg/t.

  7. Question 7 · Mine Ventilation

    The main purposes of mine ventilation include supplying fresh air and:

    1. A.Increasing the temperature of working places
    2. B.Removing dust, gases, fumes and heat
    3. C.Spreading dust evenly
    4. D.Drying the ore for processing
    Show answer

    Answer: B. Removing dust, gases, fumes and heat

    Ventilation is planned for all active workings.

  8. Question 8 · Ghana Mining Industry

    Ghana's most important mineral export by value is:

    1. A.Bauxite
    2. B.Gold
    3. C.Manganese
    4. D.Diamonds
    Show answer

    Answer: B. Gold

    Ghana is Africa's leading gold producer.

  9. Question 9 · Mining Geology, Sampling & Surveying

    Most of Ghana's primary gold deposits are hosted in:

    1. A.Young volcanic rocks of the Volta Basin
    2. B.Coastal sand dunes
    3. C.Limestone caves
    4. D.Paleoproterozoic Birimian greenstone belts
    Show answer

    Answer: D. Paleoproterozoic Birimian greenstone belts

    The Ashanti belt is a major example.

  10. Question 10 · Artisanal & Small-Scale Mining

    Mercury-free gold recovery in small-scale mining can be achieved by:

    1. A.Improved gravity concentration
    2. B.Burning amalgam in open pans at home
    3. C.Adding more mercury
    4. D.Dumping ore in rivers
    Show answer

    Answer: A. Improved gravity concentration

    Gravity methods reduce mercury exposure and pollution.

  11. Question 11 · Mine Equipment, Water & Tailings

    An LHD in underground mining is a:

    1. A.Light haul drone for surveying
    2. B.Large hydraulic drill
    3. C.Lift-hoist device
    4. D.Load-haul-dump machine
    Show answer

    Answer: D. Load-haul-dump machine

    LHDs load broken ore and carry it to ore passes or trucks.

  12. Question 12 · Ethics, Competence & Public Safety

    The paramount duty of a professional engineer is to:

    1. A.Hold public safety, health and welfare paramount
    2. B.Maximise profit for the employer on every project
    3. C.Complete projects as quickly as possible
    4. D.Please the client at any cost
    Show answer

    Answer: A. Hold public safety, health and welfare paramount

    Public safety overrides commercial pressure.

Sample flashcards

Quick facts to revise. Members can study every card with Learn, Test and Match modes.

Vehicle interaction
Segregation, rules, proximity detection
Vertical stress
~0.027 MPa/m
Acid mine drainage
Oxidising sulphides
Mining law
Minerals and Mining Act, 2006 (Act 703)
Stripping ratio
Waste ÷ ore
Powder factor
kg explosive per t (or m³)
Ventilation purpose
Fresh air; dilute dust, gas, fumes, heat
Main mineral export
Gold

Ready to practise the full Mining Engineering question bank?

Free account. Practise by topic, sit timed mock exams, study flashcards and track your readiness.

Create a free account